No |
Scope of Work |
1. |
Remove/Install Generator Rotor |
a. |
Remove fire protection lines |
b. |
Remove exciter |
c. |
Remove coupling guard |
d. |
Split LP Gen coupling |
e. |
Check and record as found alignment |
f. |
Remove top half bearings and inspect |
g. |
Remove end shields and air seals TE and GE |
h. |
Remove hydrogen seals |
i. |
Install rotor lifting device |
j. |
Remove bottom half bearings #5/#6 and inspect |
k. |
Remove inner air seals |
l. |
Install rotor belly pan |
m. |
Remove rotor lifting device |
n. |
Remove generator rotor and place on stands |
o. |
Install rotor belly pan |
p. |
Install generator rotor |
q. |
Install rotor lifting device |
r. |
Remove rotor belly pan |
s. |
Install inner air seals |
t. |
Install bottom half bearings #5/#6 |
u. |
Remove rotor lifitng device |
v. |
Recheck and record as built alignment |
w. |
Install hydrogen seals |
x. |
Install end shields and air seals TE and GE |
y. |
Install top half bearings #5/#6 |
z. |
Recouple LP and Gen rotors & install coupling guard, install exciter & fire protection lines |
2. |
Thrust Bearing Inspection |
a. |
删除前标准封面 |
b. |
Record axial float |
c. |
Removal of thrust housing top cover |
d. |
Removal and inspection of active and inactive thrust pads |
e. |
Inspect mechanical trip device |
f. |
Reinstall thrust pads (active and inactive) |
g. |
Install thrust housing top cover and record axial float |
h. |
Final installaton of front standard top cover |
3. |
Inspection of Main Lube Oil Pump Casing |
a. |
Remove top cover |
b. |
Inspect oil pump internals |
c. |
Check and record internal clearance. Make adjustments if needed |
d. |
Install top cover |
4 |
Inspection of Bearing No. 1, 2, 3, & 4 |
a. |
Removal of top and bottom half bearings and inspect/record clearances |
b. |
Polishing of journal |
c. |
Install top and bottom half bearings |
5. |
Turbine VALVE INSPECTION |
a. |
Remove GV #1 & #2 and inspect |
b. |
Remove RHS main stop valves and inspect |
c. |
Remove of IGV #1 and #2 and inspect |
d. |
Removal of Main Steam strainer and inspect |
e. |
Install GV #1 & #2 valve |
f. |
Install RHS main stop valve |
g. |
Install of IGV #1 & #2 |
h. |
Removal of Main Steam strainer and inspect |
6. |
HP/IP Turbine Inspection |
a. |
Remove manway doors from LP outer casing |
b. |
Unbolt crossover pipe |
c. |
Remove partition wall |
d. |
Remove crossover pipe |
e. |
Unbolt HP/IP split line bolts |
f. |
Remove HP/IP outer casing |
g. |
Remove inner casing and diaphragms |
h. |
Uncouple rotor from LP turbine |
i. |
Record internal clearances |
j. |
Remove HP/IP rotor |
k. |
Clean all components |
l. |
Re-install HP/IP rotor |
m. |
Remove bearing NDE and DE turbine side A & B |
n. |
Install inner casing and diaphragms |
o. |
Align rotor, check clearance and recouple to LP turbine |
p. |
Instal HP/IP outer casing |
q. |
Install all split line bolts and fully torque |
r. |
Install crossover pipe |
s. |
Install all flange bolts and fully torque |
t. |
Reinstate partition wall |
7. |
TBFP A and B Inspection |
a. |
Unbolt TBFP A and B split line bolts |
b. |
Remove TBFP A and B outer casing |
c. |
Uncouple rotor from the pump |
d. |
Remove bearing NDE and DE turbine side A & B |
e. |
Record internal clearances |
f. |
Remove TBFP A and B rotor |
g. |
Clean all components |
h. |
Re-install TBFP A and B rotor |
i. |
Install bearing NDE and DE turbine side A & B |
j. |
Record internal clearances |
k. |
Align rotor, check clearance and recouple to Pump |
l. |
Install TBFP A & B casing |
m. |
Install all split line bolts and fully torque |